Comeytrowe Major Urban Extension: Development Partner

A major urban extension consisting of 2,000 new homes, 5.25 hectares of new employment land, a new local centre, park and ride facility and a new primary school.

Our Role

  • Project management for all infrastructure delivery
  • Utilities coordination across the site
  • Cost planning and contract administration
  • Financial management and procurement
  • Resident engineer

The Outcome

  • The first homes at Comeytrowe were occupied in April 2021, and a major new roundabout on the A38 was completed in June 2022, opening up access to the western neighbourhood. The spine road which dissects the site was completed in January 2023
  • Construction of the primary school will start in spring 2023, and a pocket park and a children’s play area are both due to be completed by summer 2023

Project Highlights

  • Client: Taylor Wimpey and Vistry Group
  • Work Areas: Infrastructure project management, Utility and services coordination, financial control & QS, contract drafting, tendering and administration