Powering the Data Centre Boom:

Could a Licence Auction Help Fund the Grid?

The growth of AI and digital infrastructure is driving significant demand for new data centre capacity across the UK. However, bringing forward a viable site depends on more than securing land and planning consent. Access to sufficient power, within a programme that supports investment and delivery, is increasingly one of the key considerations.

The UK is targeting at least 6GW of AI-capable data centre capacity by 2030, compared with around 2GW today. At the same time, around 73GW across approximately 315 data centre projects is reported to be waiting in the grid connection queue.

For developers, operators and investors, this creates a practical challenge. A site can have planning potential and strong market demand, but its delivery programme ultimately depends on when sufficient power can be made available.

Planning Reform Addresses Part of the Challenge

The policy environment for data centres has evolved significantly.

Data centres were designated Critical National Infrastructure in September 2024, while changes to the consenting regime have created a potential national route for larger schemes. The draft National Policy Statement also proposes a presumption in favour of data centre development.

These measures can support the planning and consenting process, but they do not remove the underlying grid constraint.

For projects, the distinction is important. Planning certainty does not necessarily provide power certainty, and a project without a deliverable connection programme can still face significant commercial programme risk.

The question is therefore not only how the UK consents more data centres, but how the infrastructure required to support them can be delivered at the same pace.

Could Grid Certainty Have a Value?

One potential approach is to consider whether the value associated with access to scarce grid capacity could contribute towards funding additional network infrastructure.

There is precedent for government allocating scarce infrastructure rights competitively. The UK’s mobile spectrum auctions generated more than £27 billion by allocating licences to mobile network operators. However, the experience also demonstrates the importance of balancing revenue generation with the need to support infrastructure delivery.

A similar principle could potentially be explored for data centres through powered development sites.

Rather than simply providing permission to develop, designated locations could combine a defined consenting route with an agreed allocation of electrical capacity and a clearer energisation programme.

Operators could bid competitively for that certainty, with receipts used to support the grid reinforcement necessary to enable development within the relevant area.

The objective would not be to maximise the price paid by operators. It would be to establish whether some of the commercial value created by greater certainty could be reinvested in the infrastructure needed to unlock further development.

Moving Beyond Queue Position

Current connection reforms are intended to improve how projects progress through the grid connection queue, including a greater focus on project readiness.

That is an important step, but prioritising deliverable projects does not in itself create additional network capacity.

A project may be ready to proceed and still face a connection date that depends on wider reinforcement works.

A powered development model could take a different approach by linking the allocation of capacity more directly with the investment required to deliver it.

This could involve identifying locations where additional capacity can realistically be provided, establishing what reinforcement is required and allocating capacity in clearly defined phases.

For developers, the value would lie less in securing preferential treatment and more in having a clearer understanding of when power could realistically be available.

Building on AI Growth Zones

AI Growth Zones provide a potential framework through which this type of approach could be explored.

These areas already bring together considerations around power, planning and strategically important digital infrastructure. The proposed model could build on that framework by considering whether reserved capacity could be allocated competitively and whether receipts could support the infrastructure required within the zone.

This would require careful assessment.

Locations would need to be selected based on genuine network capability rather than development demand alone. Environmental constraints, land availability, transmission and distribution infrastructure, consenting requirements and the programme for reinforcement would all need to be understood before capacity could credibly be offered.

Much like the strategic land process, early technical work would therefore be important in distinguishing locations capable of supporting growth from those where infrastructure constraints fundamentally affect deliverability.

Making Connection Programmes More Deliverable

A connection date is only valuable if there is a credible infrastructure programme behind it.

That means looking beyond capacity allocation to the practical requirements for delivery.

Early work could include identifying and consenting substations and cable routes, securing the necessary land rights, completing environmental and technical investigations and planning for long-lead equipment such as transformers and switchgear.

Considering these requirements at a wider zone or infrastructure level could allow some activities to begin earlier and reduce the sequential nature of the traditional development and connection process.

It would also provide developers and investors with a clearer understanding of the dependencies that sit behind an anticipated energisation date.

Connecting Power Strategy with Development Strategy

For data centre development, power cannot be treated as a utility consideration addressed once a site has been selected.

Grid capacity, land, planning, infrastructure requirements and delivery programmes are closely connected. Decisions made in one area can materially affect the viability and programme of another.

The earlier these factors are understood together, the greater the opportunity to identify realistic development locations, test infrastructure requirements and establish a delivery strategy that reflects both development ambition and network constraints.

A competitive model for powered development rights is one potential approach. Further work would be required to understand where it could operate, how capacity should be priced and allocated, and how receipts could be used to support infrastructure investment without creating an additional barrier to development.

The wider principle is clear: supporting the next generation of UK data centres will require the strategy for digital infrastructure to develop alongside the strategy for the power infrastructure that enables it.

Planning for Power from the Outset

Early technical assessment can help developers and investors understand whether power requirements, infrastructure constraints and anticipated connection programmes align with the wider development strategy before significant commitments are made.

If you are considering a data centre development, speak to Brookbanks about bringing power, utilities, infrastructure, planning and development considerations together from the outset. Early assessment can help identify the key constraints, test assumptions and establish a clearer route towards delivery.